Production Rates: Hourly Output

What is Production Rate?

How much material a machine moves per hour or per day. Used for estimating schedule, cost, equipment needs.

Example Production Rates

EquipmentConditionCubic Yards/Hour
D6 DozerLoose soil, 150 ft push350-450
Cat 320 ExcavatorTruck loading350-500
LoaderStockpile loading90-150
GraderFinishing (slow)4-8 acres/day

Factors Affecting Production

Scheduling with Production Rates

Example: 5,000 cubic yards of cut × D6 dozer at 400 cy/hr = 12.5 hours. At 8 hrs/day = ~2 days (realistic: add 20% contingency = 2.4 days)